If your wind or solar net production budget changes, can you explain why?

Written by Andrew Brunskill | Nov 17, 2026, 11:38:14 PM

The majority of owners have a net production budget, which is important. But net production budgets often vary from year to year, so every owner should be able to answer one question: what’s driving the change?

Data from wind farms on Clir's platform shows that the median budget moves in one direction over time: down.

 

How do wind farm net production budgets compare with the preconstruction P50?

Clir compared each year's net production budget with the P50 net production in the farm's preconstruction energy yield (EY) assessment, across 103 wind farms from 26 owners on Clir's platform. The P50 is the assessment's central estimate: the annual net production it expects to be exceeded with 50% probability.

In the first three years after commercial operation, the median budget equals the P50. In year 4 the median drops to 97% of the P50, then keeps edging down to 95% by year 10.

Each dot is one year's net production budget for a wind farm, divided by the P50 net production in its preconstruction EY. The line shows the median for each year. 100+ wind farms from 25+ owners on Clir's platform with a client net budget and a preconstruction EY on file.

In other words, once a wind farm has a few years of operation behind it, the median budget is 3 to 5% below the preconstruction P50.

This analysis covers wind farms. The rest of this piece applies equally to solar plants, and so does the underlying problem, which is that many wind farms and solar plants don’t have well-defined loss budgets.

 

What drives a lower net production budget?

Net production = gross production − losses

So, if the net budget falls, either expected gross production has fallen, expected losses have risen, or both.

The cause sits with each owner, and where it involves losses, it belongs in their loss budgets: the owner’s planned allowance for each category of lost energy over a given period.

A budget can also change because its scope or basis changed, for example if a different exceedance level is targeted.

 

Should loss budgets change when the net budget does?

In many cases, yes. If the net budget moves while loss budgets stay fixed, this suggests the whole change came from expected gross production. If there are no loss budgets, the budget can’t tell you whether the change came from gross production or from losses.

Owners who do set loss budgets may vary them year to year. Preconstruction EYs typically assume the same losses every year, apart from performance degradation, and sometimes turbine availability.

 

Why does this matter for budget reconciliation?

Budget reconciliation explains the gap between what a wind farm or solar plant produced and what it was budgeted to produce. To explain where that gap came from, each loss category needs its own budget. A net budget on its own only tells you how much energy you expect to deliver. Loss budgets show where you expect to lose it.

When loss budgets are defined, Clir's platform reconciles actual against budget, category by category, and shows where the variance came from.

 

Net production budgets: common questions

What is a net production budget?

A net production budget is the amount of energy an owner expects a wind farm or solar plant to deliver over a given period, after losses.

 

What is the P50 in a preconstruction energy yield assessment?

The P50 is the assessment's central estimate: the annual net production it expects to be exceeded with 50% probability.

 

How do wind farm net production budgets compare with the P50?

Across 100+ wind farms on Clir's platform, the median budget equals the P50 in the first three years after commercial operation. It then drops to 97% of the P50 in year 4 and edges down to 95% by year 10.